ITD Cementation India Ltd. v. Konkan Railway Corporation Ltd., 2019 SCC OnLine Bom 5349 Bombay High Court, single–judge bench, G. S. Kulkarni, J.; decided on 12 December 2019 Under the arbitration clause, a “Standing Arbitral Tribunal” had to be formed within three months of the execution of the contract. The
Continue reading Categories: Appointment of arbitrator | Bias | Failure or impossibility to act | Fifth Schedule | Independence and Impartiality of arbitrator | Neutrality of arbitrator | Seventh Schedule | Standing arbitral tribunal | Termination of mandate and substitution of arbitrator | The Perkins principle