CLOSE
A. Backdrop: Section 9 and Section 17 ACA
Interim orders or injunctions “are made pending the hearing of the case, upon the merits, and they generally continue until a specified time or until a further order of the court.” [CM Row, Law of Injunctions, 9th ed., Universal 2013)]
Section 9 of the ACA gives the Court broad powers to grant interim orders before, during, or even after arbitration proceedings (but before the award is enforced).
Section 17 ACA gives the arbitral tribunal precisely the same powers to order interim measures.
Once the arbitral tribunal has been constituted, Section 9 (3) says, the Court shall not entertain an application for interim relief “unless the Court finds that circumstances exist which may not render the remedy provided under Section 17 efficacious”.
B. The facts—the court’s jurisdiction was invoked before initiating the arbitration. The dispute arose out of debenture trust deeds[1] [1] The facts of the case and the rival arguments are noted by the court in detail. It is not proposed in this Update to refer to all of them. Rather, the legal principles Harishankar J set out applied are discussed. Show More
Avantha Holdings borrowed INR 1265 crores from a consortium of lenders (KKR, L & T and BOI[2]). [2] M/s KKR India Financial Services Pvt. Ltd. and KKR India Debt Opportunities Fund (“KKR”), M/s L & T Finance Ltd., L & T Fincorp Ltd and Family Credit Ltd. (“L & T”) and M/s BOI AXA Corporate Credit Spectrum Fund (“BOI). Show More Against the borrowing, it issued non-convertible debentures. To secure certain debentures, Avantha had pledged equity shares held by it in companies called CGP and BILT[3]. [3] M/s Crompton Greaves Power and Industrial Solutions Ltd. (“CGP”) and M/s Ballarpur Industries Ltd. (“BILT”). Show More
Vistra, the respondent, was the Debenture Trustee.
The dispute related to invocation of the pledge and the consequent sale of the debentures by Vistra on the ground that Avantha committed numerous defaults.
The shares of CGIP were sold in the open market between July to November 2019. Some shares of BILT were sold on 15 July 2020 (after a notice was issued in the petition by the court), and some of it remained to be sold when the matter was heard. The sold shares were purchased by KKR and L&T.
Avantha filed an application under Section 9 ACA for grant of interim measures before commencement of the arbitration proceedings. It sought three main reliefs: –
Among the grounds on which the reliefs were based included averment that, under an oral agreement, Avantha had been negotiating an extension of time for repayment of the debentures. Also, there was a conspiracy amongst Vistra, KKR and others as a result of which the share prices were artificially depressed and then purchased[4]. [4] The argument was that a law firm which represented Vistra had tabled a report containing misleading disclosures, which led the price to fall. Show More
Hari Shankar J decided that Avantha was not entitled to any of the reliefs. His reasons and conclusions are described below.
C. Hari Shankar J’s decisions
The court started its analysis with a discussion on the “scope of Section 9 …” from paragraphs 24 to 31 (High Court’s website version).
First, the court referred to the expression “etc …” in the title of Section 9 (“Interim measures, etc. by Court”). It said that “etc.”, as has been held in several decisions, “is required to be interpreted noscitur a sociis and ejusdem generis. Therefore, it said that the measures put in place by the Court under Section have to be “interim measures”.
Then, citing to a decision of the Bombay High Court in Bank of Maharashtra v. M River Oghese, AIR 1990 Bom 107[5], the court said that interim reliefs “serve the temporary purpose of protecting the plaintiff’s interest so that the suit is not frustrated”. [5] A single judge of the Bombay High Court, GH Guttal J, interpreted the expression “interim” in a rule of the High Court which had required “a party to whom interim relief has been granted” to give an undertaking. It had been suggested that ex parte reliefs are interim and those granted after hearing are not. Show More
Continuing its discussion in the scope, the court referred to Section 17 ACA and said that: –
Continuing the discussion further the court identified the following principles governing grant of interim measures under Section 9: –
After setting out the ingredients as noted above, Hari Shankar J referred to Adhunik Steels Ltd. v. Orissa Manganese and Minerals Ltd., (2007) 7 SCC 125, and extracted four passages from it. In these passages, the Adhunik court had discussed factors to be considered in granting interim relief before an arbitral tribunal has been established, and also principles for granting a mandatory interim injunction. Hari Shankar J then said that the manner in which the court applied the principles is “also instructive”.[9] [9] Adhunik was granted a 10 years renewable lease by Orissa Manganese. Adhunik deployed resources for the mining operations and incurred considerable expenditure. Merely months later, Orissa gave the notice to terminate the lease saying the grant was against the rules. Adhunik applied for an interim mandatory injunction to continue the lease. The Supreme Court directed Orissa not to grant the lease to any other party but also ordered that Orissa was entitled to carry on the operations by itself. The Supreme Court reasoned that Orissa carrying on the activity will not prejudice Adhunik because if it succeeds in the arbitration, Adhunik would be entitled to get compensation for termination. It is these passages that Hari Shankar J emphasized on. Show More
He then also referred to Arvind Constructions Ltd. v. Kalinga Mining Corporation, (2007) 6 SCC 798, which he said: “reiterated the principle that the exercise of jurisdiction, under Section 9 of the 1996 Act, is subject to the restrictions and limitations contained in the Specific Relief Act.”
He also referred to Firm Ashok Traders v. Gurmukh Das Saluja, (2004) 3 SCC 155 to have said that “the Court under Section 9 is only formulating interim measures so as to protect the right under adjudication before the Arbitral Tribunal from being frustrated”.
Then, he noted Olex Facas Pvt Ltd. v. Skoda Export Co. Ltd., AIR 2000 Del 161, where Dalveer Bhandari J, then in the Delhi High Court, had said that the court’s discretionary power to grant interim relief should be exercised “where there is adequate material on record, leading to a definite conclusion that the respondent is likely to render the entire arbitration proceedings infructuous, by frittering away the properties of funds either before or during the pendency of arbitration proceedings or even during the interregnum period from the date of award and its execution”.
Hari Shankar J then set out the clauses of Section 9 and commented on “the ambit of sub-clause (ii)(e) of sub-section (1) of Section 9, which empowers the Court to grant ―such other interim measure of protection as may appear to the court to be just and convenient.” He referred to Madras High Court’s Sekar v. Akash Housing, where Banumathi J had noted that the jurisdiction under the “just and convenient” clause “is quite while (sic wide) in amplitude, but must be exercised with restraint. Interim measures are to be granted by the Court so as to protect the rights in adjudication before the arbitral tribunal from being frustrated”.
After referring to the principles and the authorities in the manner described above, Hari Shankar J considered the merits of the case under the heading “the cause of action, and the prayers, in the petition”. He started by saying that “tested on the touchstone of the above principles, it becomes apparent that none of the prayers, in this petition can be granted, under Section 9.”
He also made a finding, after a crisp summary of the facts, that Avantha’s case was “featherweight”.
As to the relief of transferring the pledged CGP shares, Hari Shankar J concluded that no interim direction could be issued because the pledge had already been involved and a majority of the shares had already been sold in the open market. “Howsoever wide its amplitude”, he noted, Section 9 “cannot justify setting the clock back to a stage anterior to the invocation of the pledge, by [Vistra], which took place as far back as in March 2019”.
As to the sale of BILT shares, he assessed the merits of the claim and found that there was no occasion “to interdict the invocation and sale, if any, of the pledged BILT shares.”He said that “any such direction, by this Court, would amount to a proscription, on [Vistra] exercising the rights, conferred and vested in them by the covenants of the Debenture Trust Deeds. This, on the face of it, is impermissible; in any case, no such relief can be granted, in a proceeding under Section 9 of the 1996 Act”.
Lastly, Harishankar J considered Avantha’s prayer seeking a restraint on Vistra from taking any steps under the underlying contract and documents. This was rejected on the ground that apart from the fact that it amounted to an “absolute embargo” on Vistra from exercising its contractual rights, there was no denial by Avantha of the alleged default. He found that the prayer was “premised on the theory” that the underlying contracts had been rescinded, which he said had no merit.He also rejected an argument of bad faith, which was advanced citing to Mardia Chemicals Ltd v. UOI, (2004) 4 SCC 311 (“lenders owe a duty to act fairly and in good faith”). Hari Shankar J said that while there was “gainsaying this proposition”, it was completely irrelevant to the issue because the dispute was purely contractual, and the argument of bad faith had been raised in the context of allegedly artificially depressing the share price before purchasing them. This dispute, he noted, was “foreign to the arbitration agreement” and not the subject-matter of Section 9.