CLOSE
19 April 2021 | Maharashtra State Road Development v. PLUS BKSP Toll Ltd. | BP Colabawalla J | 2021 SCC OnLine Bom 607
Disputes between the parties arose out of a concession agreement and its termination. The tribunal conducted the arbitration trial over a few days. It heard the final arguments and gave the parties time to file written submissions. It made clear there would be no more hearings unless it required clarifications.
But the tribunal rendered in PLUS’ favour what it styled an “interim award” in which it decided on the validity of the termination and MSRDC’s liability to pay. Then, it deferred to a second phase of the arbitration, the issue of quantum in which PLUS was allowed to make a fresh claim on the quantum. It also deferred to the second round a decision on MSRDC’s counterclaims. Also, the tribunal specifically rejected some of PLUS’ claims and expressed inability to decide on the others for lack of evidence.
The court ruled that there was a breach of Section 19 (2) ACA, legal misconduct, and failure to decide MSRDC’s counterclaim:-
Therefore, the interim award was set aside to the extent that it had allowed parties to file fresh pleadings and lead further evidence.
Access the judgement here.